Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Kosmos Vinayak Tower RERA Details - P51800009164, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kosmos Vinayak Tower under registration P51800009164 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800009164
  • Project Name VINAYAK TOWER
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Borivali
  • Original Completion 31 December 2019
  • Revised Completion 30 June 2023
  • Project Area (in Sq.mt.) 543.7
  • Total Buildings/Towers 1
  • Documents 8 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 19 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name KOSMOS DEVELOPER
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Sankalp VigneshwaraPushpapark Road No.2 Near Siddhivinayak2120CompletedResidential / Group Housing1492013-10-112013-11-11NoNA

Promoters, Co-promoters & Members

NameRoleAddress
PREETI RAKESH SINGHPartnerMumbai Suburban, MAHARASHTRA
PREETI RAKESH SINGHPartnerMumbai Suburban, MAHARASHTRA
PREETI RAKESH SINGHPartnerMumbai Suburban, MAHARASHTRA
PREETI RAKESH SINGHPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
VINAYAK TOWER VINAYAK TOWER 8 2 21 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 37
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 33 units · avg area 34.28 Sq.mt.
2 BHK 2 units · avg area 51.47 Sq.mt.
SHOP 2 units · avg area 13.84 Sq.mt.
  • VINAYAK TOWER
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 34.75 26 19
SHOP 13.84 2 2
1BHK 37.53 1 1
2BHK 51.47 2 0
1BHK 31.68 6 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VINAYAK TOWER
VINAYAK TOWER · Overall Progress 47%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 Plan Bhatekar.PDF.Pdf
2 Kosmos Pan Card.Pdf.Pdf
3 Vinayak Title Certificat.Pdf.Pdf
4 Compressed Affidafit.Pdf.Pdf
5 Bhatawadekar Agreement RERA.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Branch Address DAHISAR WEST, MUMBAI 400068
Country/City