residential New Launch Source: rera.mh

Mohanraj CHS RERA Details - P51800081101, Mumbai

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Mohanraj CHS under registration P51800081101 in Mumbai, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51800081101
  • Project Name MOHANRAJ CHS LTD
  • Project Type Residential / Group Housing
  • Project Status New Launch
  • State Maharashtra
  • District Mumbai Suburban
  • Taluka Borivali
  • Village Kandivali
  • Original Completion 12 March 2028
  • Revised Completion 12 March 2028
  • Project Area (in Sq.mt.) 1,201.0
  • Total Buildings/Towers 2
  • Documents 36 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 March 2026 Expected commencement of civil works and foundation on site.
Original Completion 12 March 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 12 March 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name MOHAN ENTERPRISES

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MOHANRAJ CHS LTD WING A 17 0 10 0 0 NA
MOHANRAJ CHS LTD WING B 16 0 10 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 71
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 27 units · avg area 40.97 Sq.mt.
2 BHK 12 units · avg area 57.90 Sq.mt.
REHAB UNIT 32 units · avg area 44.66 Sq.mt.
  • WING A
  • WING B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
REHAB UNIT 41.34 2 0
REHAB UNIT 51.28 2 0
1BHK 39.11 1 0
REHAB UNIT 59.09 1 0
REHAB UNIT 59.83 5 0
REHAB UNIT 32.33 5 0
REHAB UNIT 39.11 1 0
1BHK 41.34 7 0
2BHK 59.83 4 0
1BHK 39.58 2 0
2BHK 59.09 6 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • WING A
  • WING B
WING A · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Proforma Of Allotment Letter.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
9 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
10 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 2 Commencement Certificates NA Order For Plotted Development.Pdf
13 3 Commencement Certificates NA Order For Plotted Development.Pdf
14 1 Building Plan Approval NA Order For Plotted Development.Pdf
15 2 Building Plan Approval NA Order For Plotted Development.Pdf
16 3 Other – Legal.Pdf
17 1 Other – Legal.Pdf
18 2 Other – Legal.Pdf
19 1 Declaration About Commencement Certificate.Pdf
20 1 CERSAI Details.Pdf
21 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
22 1 Deviation Report With Respect To Allotment Letter.Pdf
23 1 B Details Of Encumbrances Concerned To Legal.Pdf
24 2 B Details Of Encumbrances Concerned To Legal.Pdf
25 1 Other – Finance.Pdf
26 1 Other – Technical.Pdf
27 3 Other – Technical.Pdf
28 2 Other – Technical.Pdf
29 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
30 1 Proforma Of Agreement For Sale.Pdf
31 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
32 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
33 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
34 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
IFSC BCBM0000016
Branch Address KANDIVALI WEST MUMBAI
Country/City