residential Partially Ready To Move Source: rera.ka

Ecolife Eon Akash RERA Details - PRM/KA/RERA/1251/446/PR/300323/005832 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ecolife Eon Akash under registration PRM/KA/RERA/1251/446/PR/300323/005832 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1251/446/PR/300323/005832
  • Project Name EON AKASH B & C
  • Project Type Residential/Group Housing
  • Project Status Partially Ready To Move
  • District Bengaluru Urban
  • Taluka Bengaluru East
  • Original Completion 31 July 2026
  • Documents 68 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 19 December 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 July 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

ECO LIFE DEVELOPERS
Registered Address No.28, RMS colony,1st main Bhattarahalli, K R Puram ,Bengaluru North ,Bengaluru Urban-560049
Experience Details
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address KHATA NO 746/20/746, SY NO 20,21/2,21/3,21/7 (OLD SY NO 21/3) & 22 AT BALAGERE VILLAGE, VARTHUR HOBL , WHITE FIELD SUB-DIVISION, WARD NO-149, MAHADEVAPURA ZONE, BENGALURU EAST , Bengaluru East , Bengaluru Urban, Karnataka - 560087

RERA Coordinates

Latitude, Longitude 12.937579178267562, 77.73311146544141
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. BBMP/Addl.Dir/JDNORTH/0080/21-252
Authority BBMP - Bruhat Bengaluru Mahanagara Palike
Approved Date 14 December 2022

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
B 1 16 1 210 Residential 44.99 14 112
C 1 16 1 98 Residential 44.99 14 98

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 0 units
  • B
  • C
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
GF 3 BHK 111 B101
GF 3 BHK 98 B102
GF 3 BHK 108 B103
GF 3 BHK 95 B104
GF 3 BHK 95 B105
GF 3 BHK 95 B106
GF 3 BHK 95 B107
GF 3 BHK 95 B108
1 3 BHK 111 B201
1 3 BHK 98 B202
1 3 BHK 108 B203
1 3 BHK 95 B204
1 3 BHK 95 B205
1 3 BHK 95 B206
1 3 BHK 95 B207
1 3 BHK 95 B208
2 3 BHK 111 B301
2 3 BHK 98 B302
2 3 BHK 108 B303
2 3 BHK 95 B304
2 3 BHK 95 B305
2 3 BHK 95 B306
2 3 BHK 95 B307
2 3 BHK 95 B308
3 3 BHK 111 B401
3 3 BHK 98 B402
3 3 BHK 108 B403
3 3 BHK 95 B404
3 3 BHK 95 B405
3 3 BHK 95 B406
3 3 BHK 95 B407
3 3 BHK 95 B408
4 3 BHK 111 B501
4 3 BHK 98 B502
4 3 BHK 108 B503
4 3 BHK 95 B504
4 3 BHK 95 B505
4 3 BHK 95 B506
4 3 BHK 95 B507
4 3 BHK 85 B508
5 3 BHK 114 B601
5 3 BHK 102 B602
5 3 BHK 104 B603
5 3 BHK 99 B604
5 3 BHK 99 B605
5 3 BHK 96 B606
5 3 BHK 96 B607
5 3 BHK 96 B608
6 3 BHK 114 B701
6 3 BHK 102 B702
6 3 BHK 104 B703
6 3 BHK 99 B704
6 3 BHK 99 B705
6 3 BHK 96 B706
6 3 BHK 96 B707
6 3 BHK 96 B708
7 3 BHK 111 B801
7 3 BHK 98 B802
7 3 BHK 108 B803
7 3 BHK 95 B804
7 3 BHK 95 B805
7 3 BHK 95 B806
7 3 BHK 95 B807
7 3 BHK 95 B808
8 3 BHK 111 B901
8 3 BHK 98 B902
8 3 BHK 108 B903
8 3 BHK 95 B904
8 3 BHK 95 B905
8 3 BHK 95 B906
8 3 BHK 95 B907
8 3 BHK 95 B908
9 3 BHK 111 B1001
9 3 BHK 98 B1002
9 3 BHK 108 B1003
9 3 BHK 95 B1004
9 3 BHK 95 B1005
9 3 BHK 95 B1006
9 3 BHK 95 B1007
9 3 BHK 95 B1008
10 3 BHK 111 B1101
10 3 BHK 98 B1102
10 3 BHK 108 B1103
10 3 BHK 95 B1104
10 3 BHK 95 B1105
10 3 BHK 95 B1106
10 3 BHK 95 B1107
10 3 BHK 95 B1108
11 3 BHK 114 B1201
11 3 BHK 102 B1202
11 3 BHK 104 B1203
11 3 BHK 99 B1204
11 3 BHK 99 B1205
11 3 BHK 96 B1206
11 3 BHK 96 B1207
11 3 BHK 96 B1208
12 3 BHK 114 B1301
12 3 BHK 102 B1302
12 3 BHK 104 B1303
12 3 BHK 99 B1304
12 3 BHK 99 B1305
12 3 BHK 96 B1306
12 3 BHK 96 B1307
12 3 BHK 96 B1308
13 3 BHK 114 B1401
13 3 BHK 102 B1402
13 3 BHK 104 B1403
13 3 BHK 99 B1404
13 3 BHK 99 B1405
13 3 BHK 96 B1406
13 3 BHK 96 B1407
13 3 BHK 96 B1408
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Sub Structure Earth Work And Other Leveling Preparation Work % not reported Sub Structure Foundation Footing Work % not reported Sub Structure Upto Plinth Level % not reported
Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported Sub Structure Retaining Wall (All Types) % not reported Sup Structure Rcc Or Ms Framed Structure % not reported
Sup Structure Masonry Construction % not reported Sup Structure Plastering Inside , Outside & Ceiling % not reported Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported
Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported Sup Structure Railing And Grill Fixing % not reported
Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported Finishing Works Painting % not reported Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported
Finishing Works Weather Proof Work(tile,concrete) % not reported Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported Finishing Works Elevation Work % not reported
Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported Internal Infrastructure Water Supply % not reported Internal Infrastructure Sewage And Drainage System % not reported
Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported Internal Infrastructure Energy Management % not reported Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported
Internal Infrastructure Solid Waste Management And Disposal % not reported Internal Infrastructure Emergency Evacuation Services % not reported External Infrastructure Water Supply % not reported
External Infrastructure Internal Roads & Footpaths % not reported External Infrastructure Sewage And Drainage System % not reported External Infrastructure Electricity Supply Transformer And Substation % not reported
External Infrastructure Solid Waste Management And Disposal % not reported External Infrastructure Emergency Evacuation Services % not reported External Infrastructure Storm Water Drains % not reported
External Infrastructure Use Of Renewable Energy % not reported External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported External Infrastructure Fire Protection And Fire Safety Requirements % not reported
External Infrastructure Sewage Treatment Plant (Stp) % not reported External Infrastructure Parks & Tree Planting % not reported External Infrastructure Street Lighting % not reported
Amenities Electricity % not reported Amenities Smart Home Automation % not reported Amenities Cctv Surveillance % not reported
Amenities Club House % not reported Amenities Community Hall % not reported Amenities Outdoor Sports Facility % not reported
Amenities Indoor Sports Facility % not reported Amenities Swimming Pool % not reported Amenities Gym % not reported
Amenities Parks % not reported Amenities Power Backup % not reported Amenities Piped Gas % not reported
Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported Common Areas Staircases % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
1 Completion Certificate
Fd 1 Balance Sheet Mar2022.Pdf
Fd 2 Balance Sheet Mar 2021.Pdf
Fd 3 Balance Sheet Mar 2020 Compressed Compressed (1).Pdf
Fd 4 P And L Account 2022.Pdf
Fd 5 P And L Account 2021.Pdf
Fd 6 P And L Account 2020 Compressed.Pdf
Fd 7 NOT APPLICABLE.Pdf
Fd 8 NOT APPLICABLE.Pdf
Fd 9 NOT APPLICABLE.Pdf
Fd 10 NOT APPLICABLE.Pdf
Fd 11 NOT APPLICABLE.Pdf
Fd 12 NOT APPLICABLE.Pdf
Fd 13 Form 3CB-3CD FY 2021-22.Pdf
Fd 14 3CD Form-FY 2020-21.Pdf
Fd 15 Audit Report 2020.Pdf
Fd 16 ITRV - Acknowledgement.Pdf
Fd 17 ITRV - Acknowledgementpdf 2020-21.Pdf
Fd 18 ITRV - Acknowledgementpdf 2019-20.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 6 Approved Building Plotting Plan*( Annexure - 71 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 11 Approved Section Of Building Infrastructure Plan Of Plotting*( Annexure - 76 )
Pd 12 Area Development Plan Of Project Area*( Annexure - 77 )
Pd 13 Certificate From Registered Engineer Indicating The Structural Safety Of The Building*( Annexure - 78 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 19 Conversion Certificate Under Section 95 Of The KLR Act 1964*( Annexure - 84 )
Pd 20 Any Other Document (Rights Title Interest Name)*( Annexure - 85 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Pd 22 Proforma Of Allotment Letter*( Annexure - 87 )
Pd 24 Brochure*( Annexure - 89 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 1 ESCOM Electricity*( Annexure - 93 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 5 Fire Force Department( Annexure - 97 )
Noc 6 Airport Authority Of India( Annexure - 98 )
Noc 7 KSPCB( Annexure - 99 )
Noc 8 SEIAA( Annexure - 100 )
Noc 9 BSNL( Annexure - 101 )
Dr 3 Relinquishment Deed( Annexure - 110 )
Photo 1 Project Photo
Ed 1 08-02-2023
Ed 2 08-02-2023
Ed 3 08-02-2023
Ed 4 08-02-2023
Ed 5 08-02-2023
Ed 6 08-02-2023
Ed 7 08-02-2023
Ed 8 08-02-2023
Ed 9 08-02-2023
Ed 10 08-02-2023
Ed 11 04-03-2023
Ed 12 04-03-2023
Ed 13 04-03-2023
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Axis Bank
Account Number (RERA) 923020001974892
IFSC UTIB0003749
Branch Address VARTHUR
Country/City