Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.ka

Bhartiya City Nikoo Homes 6 RERA Details - PRM/KA/RERA/1251/309/PR/160124/006550 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Bhartiya City Nikoo Homes 6 under registration PRM/KA/RERA/1251/309/PR/160124/006550 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1251/309/PR/160124/006550
  • Project Name Nikoo Homes VI - Phase-2
  • Project Type Residential/Group Housing
  • Project Status Under Construction
  • District Bengaluru Urban
  • Taluka Bengaluru North
  • Original Completion 30 September 2029
  • Documents 84 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 October 2024 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2029 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

Bhartiya Urban Private Limited
Registered Address No.1/5,Palace Road ,Bengaluru North ,Bengaluru Urban-560001
Experience Details
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address Survey No 53 of Kogilu Village , Yelahanka Hobli, Yelahanka Taluk , Bengaluru North , Bengaluru Urban, Karnataka - 560064

RERA Coordinates

Latitude, Longitude 13.104793310299922, 77.60908484458923
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. BBMP/Addl.Dir/JDNORTH/0024/23-24
Authority BBMP - Bruhat Bengaluru Mahanagara Palike
Approved Date 17 October 2023

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
Tower - D 2 18 0 143 Residential 50.6 16 126
Tower - E 2 18 0 141 Residential 50.6 16 141

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 0 units
2 BHK 0 units
3 BHK 0 units
4 BHK 0 units
Studio 0 units
  • Tower - D
  • Tower - E
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
-1 3 BHK 94.67 D-003
-1 3 BHK + Study 111.39 D-007
-1 4 BHK 151.15 D-008
GF 3 BHK 94.67 D-013
GF 3 BHK + Study 111.39 D-017
GF 4 BHK 151.15 D-018
1 2 BHK + Study 79.25 D-021
1 2 BHK + Study 79.25 D-022
1 3 BHK 94.67 D-023
1 3 BHK 94.67 D-024
1 2 BHK 70.51 D-025
1 2 BHK 70.51 D-026
1 3 BHK + Study 111.39 D-027
1 4 BHK 151.15 D-028
2 2 BHK + Study 79.25 D-031
2 2 BHK + Study 79.25 D-032
2 3 BHK 94.67 D-033
2 3 BHK 94.67 D-034
2 2 BHK 70.51 D-035
2 2 BHK 70.51 D-036
2 3 BHK + Study 111.39 D-037
2 4 BHK 151.15 D-038
3 2 BHK + Study 79.25 D-041
3 2 BHK + Study 79.25 D-042
3 3 BHK 94.67 D-043
3 3 BHK 94.67 D-044
3 2 BHK 70.51 D-045
3 2 BHK 70.51 D-046
3 3 BHK + Study 111.39 D-047
3 4 BHK 151.15 D-048
4 2 BHK + Study 79.25 D-051
4 2 BHK + Study 79.25 D-052
4 3 BHK 94.67 D-053
4 3 BHK 94.67 D-054
4 2 BHK 70.51 D-055
4 2 BHK 70.51 D-056
4 3 BHK + Study 111.39 D-057
4 4 BHK 151.15 D-058
5 2 BHK + Study 79.25 D-061
5 2 BHK + Study 79.25 D-062
5 3 BHK 94.67 D-063
5 3 BHK 94.67 D-064
5 2 BHK 70.51 D-065
5 2 BHK 70.51 D-066
5 3 BHK + Study 111.39 D-067
5 4 BHK 151.15 D-068
6 2 BHK + Study 79.25 D-071
6 2 BHK + Study 79.25 D-072
6 3 BHK 94.67 D-073
6 3 BHK 94.67 D-074
6 2 BHK 70.51 D-075
6 2 BHK 70.51 D-076
6 3 BHK + Study 111.39 D-077
6 4 BHK 151.15 D-078
7 2 BHK + Study 79.25 D-081
7 2 BHK + Study 79.25 D-082
7 3 BHK 94.67 D-083
7 3 BHK 94.67 D-084
7 2 BHK 70.51 D-085
7 2 BHK 70.51 D-086
7 3 BHK + Study 111.39 D-087
7 4 BHK 151.15 D-088
8 2 BHK + Study 79.25 D-091
8 2 BHK + Study 79.25 D-092
8 3 BHK 94.67 D-093
8 3 BHK 94.67 D-094
8 2 BHK 70.51 D-095
8 2 BHK 70.51 D-096
8 3 BHK + Study 111.39 D-097
8 4 BHK 151.15 D-098
9 2 BHK + Study 79.25 D-101
9 2 BHK + Study 79.25 D-102
9 3 BHK 94.67 D-103
9 3 BHK 94.67 D-104
9 2 BHK 70.51 D-105
9 2 BHK 70.51 D-106
9 3 BHK + Study 111.39 D-107
9 4 BHK 151.15 D-108
10 2 BHK + Study 79.25 D-111
10 2 BHK + Study 79.25 D-112
10 3 BHK 94.67 D-113
10 3 BHK 94.67 D-114
10 2 BHK 70.51 D-115
10 2 BHK 70.51 D-116
10 3 BHK + Study 111.39 D-117
10 4 BHK 151.15 D-118
11 2 BHK + Study 79.25 D-121
11 2 BHK + Study 79.25 D-122
11 3 BHK 94.67 D-123
11 3 BHK 94.67 D-124
11 2 BHK 70.51 D-125
11 2 BHK 70.51 D-126
11 3 BHK + Study 111.39 D-127
11 4 BHK 151.15 D-128
12 2 BHK + Study 79.25 D-131
12 2 BHK + Study 79.25 D-132
12 3 BHK 94.67 D-133
12 3 BHK 94.67 D-134
12 2 BHK 70.51 D-135
12 2 BHK 70.51 D-136
12 3 BHK + Study 111.39 D-137
12 4 BHK 151.15 D-138
13 2 BHK + Study 79.25 D-141
13 2 BHK + Study 79.25 D-142
13 3 BHK 94.67 D-143
13 3 BHK 94.67 D-144
13 2 BHK 70.51 D-145
13 2 BHK 70.51 D-146
13 3 BHK + Study 111.39 D-147
13 4 BHK 151.15 D-148
14 2 BHK + Study 79.25 D-151
14 2 BHK + Study 79.25 D-152
14 3 BHK 94.67 D-153
14 3 BHK 94.67 D-154
14 2 BHK 70.51 D-155
14 2 BHK 70.51 D-156
14 3 BHK + Study 111.39 D-157
14 4 BHK 151.15 D-158
15 2 BHK + Study 79.25 D-161
15 2 BHK + Study 79.25 D-162
15 3 BHK 94.67 D-163
15 3 BHK 94.67 D-164
15 2 BHK 70.51 D-165
15 2 BHK 70.51 D-166
15 3 BHK + Study 111.39 D-167
15 4 BHK 151.15 D-168
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Sub Structure Earth Work And Other Leveling Preparation Work % not reported Sub Structure Foundation Footing Work % not reported Sub Structure Upto Plinth Level % not reported
Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported Sub Structure Retaining Wall (All Types) % not reported Sup Structure Rcc Or Ms Framed Structure % not reported
Sup Structure Masonry Construction % not reported Sup Structure Plastering Inside , Outside & Ceiling % not reported Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported
Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported Sup Structure Railing And Grill Fixing % not reported
Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported Finishing Works Painting % not reported Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported
Finishing Works Weather Proof Work(tile,concrete) % not reported Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported Finishing Works Elevation Work % not reported
Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported Internal Infrastructure Water Supply % not reported Internal Infrastructure Sewage And Drainage System % not reported
Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported Internal Infrastructure Energy Management % not reported Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported
Internal Infrastructure Solid Waste Management And Disposal % not reported Internal Infrastructure Emergency Evacuation Services % not reported External Infrastructure Water Supply % not reported
External Infrastructure Internal Roads & Footpaths % not reported External Infrastructure Sewage And Drainage System % not reported External Infrastructure Electricity Supply Transformer And Substation % not reported
External Infrastructure Solid Waste Management And Disposal % not reported External Infrastructure Emergency Evacuation Services % not reported External Infrastructure Storm Water Drains % not reported
External Infrastructure Use Of Renewable Energy % not reported External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported External Infrastructure Fire Protection And Fire Safety Requirements % not reported
External Infrastructure Sewage Treatment Plant (Stp) % not reported External Infrastructure Parks & Tree Planting % not reported External Infrastructure Street Lighting % not reported
Amenities Electricity % not reported Amenities Smart Home Automation % not reported Amenities Cctv Surveillance % not reported
Amenities Club House % not reported Amenities Community Hall % not reported Amenities Outdoor Sports Facility % not reported
Amenities Indoor Sports Facility % not reported Amenities Swimming Pool % not reported Amenities Gym % not reported
Amenities Parks % not reported Amenities Power Backup % not reported Amenities Piped Gas % not reported
Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported Common Areas Staircases % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
1 Completion Certificate
2 Completion Certificate
3 Completion Certificate
4 Completion Certificate
Fd 1 Balance Sheet - FY 2022-23.Pdf
Fd 2 Balance Sheet - FY 2021-22.Pdf
Fd 3 Balance Sheet - FY 2020-21.Pdf
Fd 4 P & L Account - FY 2022-23.Pdf
Fd 5 P & L Account - FY 2021-22.Pdf
Fd 6 P & L Account - FY 2020-21.Pdf
Fd 7 Directors Report 2022-23.Pdf
Fd 8 Directors Report 2021-22.Pdf
Fd 9 Directors Report 2020-21.Pdf
Fd 10 CFS - FY 2022-23.Pdf
Fd 11 CFS - FY 2021-22.Pdf
Fd 12 CFS - FY 2020-21.Pdf
Fd 13 Audit Report 2022-23.Pdf
Fd 14 Audit Report 2021-22.Pdf
Fd 15 Audit Report 2020-21.Pdf
Fd 16 ITR FY 2022-23.Pdf
Fd 17 ITR FY 2021-22.Pdf
Fd 18 ITR FY 2020-21.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 2 Commencement Certificate*( Annexure - 67 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 5 Approved Layout Plan*( Annexure - 70 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 13 Certificate From Registered Engineer Indicating The Structural Safety Of The Building*( Annexure - 78 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 16 Collaboration Agreement Development Agreement Joint Development Agreement Other Agreement*( Annexure - 81 )
Pd 19 Conversion Certificate Under Section 95 Of The KLR Act 1964*( Annexure - 84 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Pd 22 Proforma Of Allotment Letter*( Annexure - 87 )
Pd 24 Brochure*( Annexure - 89 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 1 ESCOM Electricity*( Annexure - 93 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 3 Approval NOC Under Section 109 Of KLR Act 1961( Annexure - 95 )
Noc 5 Fire Force Department( Annexure - 97 )
Noc 6 Airport Authority Of India( Annexure - 98 )
Noc 7 KSPCB( Annexure - 99 )
Noc 8 SEIAA( Annexure - 100 )
Noc 9 BSNL( Annexure - 101 )
Photo 1 Project Photo
Od 1 Master Plan Extract Thanisanda CDP.Pdf
Od 2 Village Map.Pdf
Od 3 BDA Work Order.Pdf
Od 4 Building Plan - Nikoo VI - Ph2 - Demarcated.Pdf
Od 5 Area Details - Typewise.Pdf
Od 6 Building Plan - Nikoo VI-1-Site Plan.Pdf
Od 7 Building Plan - Nikoo VI-13-Section.Pdf
Od 8 Building Plan - Nikoo VI-14-Elevation.Pdf
Od 9 Building Plan - Nikoo VI-3-1st Basement Block 1 To 3.Pdf
Od 10 Building Plan - Nikoo VI-2-2nd Basement Plan.Pdf
Od 11 Building Plan - Nikoo VI-4-Ground Floor.Pdf
Od 12 Building Plan - Nikoo VI-5-Ground Floor Block 1 & 2.Pdf
Od 13 Building Plan - Nikoo VI-6-1st Floor Plan Block 1 & 2.Pdf
Od 14 Building Plan - Nikoo VI-7-2nd & Terrace Floor Plan.Pdf
Od 15 Building Plan - Nikoo VI-8-Typical 3th, 5th, 7th, 9th, 11th, 13th, 15th & 17th Floor Plan.Pdf
Od 16 Building Plan - Nikoo VI-9-Typical 4th, 6th, 8th, 10th, 12th, 14th & 16th Floor Plan.Pdf
Od 17 Building Plan - Nikoo VI-10-Terrace - Wing-1 2 & 3.Pdf
Od 18 Building Plan - Nikoo VI-11-Ground, 1st & 2nd Floor Plan - Wing 4 & 5.Pdf
Od 19 Building Plan - Nikoo VI-12-Typical 3rd To 16th & Terrace Floor Plan - Wing 4 & 5.Pdf
Ed 1 04-01-2024
Ed 2 04-01-2024
Ed 3 04-01-2024
Ed 4 04-01-2024
Ed 5 04-01-2024
Ed 6 04-01-2024
Ed 7 04-01-2024
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Sale Deed
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Standard Chartered Bank
Account Number (RERA) 45605182826
IFSC SCBL0036074
Branch Address MG ROAD
Country/City