Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.ka

Trifecta Vanto RERA Details - PRM/KA/RERA/1251/446/PR/190424/006813 Bangalore

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Trifecta Vanto under registration PRM/KA/RERA/1251/446/PR/190424/006813 in Bangalore, Karnataka. Data is sourced from rera.ka.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PRM/KA/RERA/1251/446/PR/190424/006813
  • Project Name TRIFECTA VANTO PHASE-1
  • Project Type Residential/Group Housing
  • Project Status Under Construction
  • District Bengaluru Urban
  • Taluka Bengaluru East
  • Original Completion 31 August 2027
  • Documents 133 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 March 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 August 2027 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Primary Promoter

TRIFECTA PROJECTS PRIVATE LIMITED
Registered Address SY.66/2,67/1, OPP BESCOM OFFICE, WHITE FIEL MAIN ROAD, GARUDHACHARPALYA, ,MAHADEVAPURA, Bengaluru North, Bengaluru Urban, ,Bengaluru North ,Bengaluru Urban-560048
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address Sy. No. 37/2,37/3,37/4,37/5,37/6,37/7P,37/8,37/9,37/10,37/11,37/12,37/13,37/14,37/15,37/16,37/17,37/18,37/19,37/20,43/4B and 43/5 , Bangalore Urban, , Bengaluru East , Bengaluru Urban, Karnataka - 560035

RERA Coordinates

Latitude, Longitude 12.880757277999383, 77.71537779886503
Plans

Plans & Approvals

Statutory approvals obtained or pending against the project site.

Plan Approval No. BDA/EM/EO-1/TA-2/E/59 & 60/2023-24
Authority BDA - Bangalore Development Authority
Approved Date 05 March 2024

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Name No. of Basements No. of Slab No. of Slits No. of Open Parking Building Type Height of Tower No. of Floors No. of Units
A 1 26 1 450 Residential 77.0 24 450
B 1 26 1 375 Residential 77.0 24 375

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units -
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 0 units
2 BHK 0 units
3 BHK 0 units
5 BHK 0 units
  • A
  • B
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area No. of Unit
-1 3BHK 85.96 001
-1 3BHK(3T) 89.36 002
-1 2BHK 65.52 003
-1 2BHK 65.52 004
-1 3BHK 83.27 005
-1 3BHK 80.78 006
-1 3BHK 83.27 007
-1 3BHK 81.29 008
-1 2BHK 64.96 009
-1 2BHK+STUDY 69.26 010
-1 2BHK+STUDY 73.01 011
-1 2BHK 64.96 012
-1 1BHK 40.91 013
-1 1BHK 40.91 014
-1 3BHK 83.27 015
-1 2BHK+STUDY 69.26 016
-1 3BHK 80.59 017
-1 3BHK 83.27 018
GF 3BHK 85.96 101
GF 3BHK(3T) 89.36 102
GF 2BHK 65.52 103
GF 2BHK 65.52 104
GF 3BHK 83.27 105
GF 3BHK 80.78 106
GF 3BHK 83.27 107
GF 3BHK 81.29 108
GF 2BHK 64.96 109
GF 2BHK+STUDY 69.26 110
GF 2.5BHK 73.01 111
GF 2BHK 64.96 112
GF 1BHK 40.91 113
GF 1BHK 40.91 114
GF 3BHK 83.27 115
GF 2BHK+STUDY 69.26 116
GF 3BHK 80.59 117
GF 3BHK 83.27 118
1 3BHK 85.96 201
1 3BHK(3T) 89.36 202
1 2BHK 65.52 203
1 2BHK 65.52 204
1 3BHK 83.27 205
1 3BHK 80.78 206
1 3BHK 83.27 207
1 3BHK 81.29 208
1 2BHK 64.96 209
1 2BHK+STUDY 69.26 210
1 2.5BHK 73.01 211
1 2BHK 64.96 212
1 1BHK 40.91 213
1 1BHK 40.91 214
1 3BHK 83.27 215
1 2BHK+STUDY 69.26 216
1 3BHK 80.59 217
1 3BHK 83.27 218
2 3BHK 85.96 301
2 3BHK(3T) 89.36 302
2 2BHK 65.52 303
2 2BHK 65.52 304
2 3BHK 83.27 305
2 3BHK 80.78 306
2 3BHK 83.27 307
2 3BHK 81.29 308
2 2BHK 64.96 309
2 2BHK+STUDY 69.26 310
2 2.5BHK 73.01 311
2 2BHK 64.96 312
2 1BHK 40.91 313
2 1BHK 40.91 314
2 3BHK 83.27 315
2 2BHK+STUDY 69.26 316
2 3BHK 80.59 317
2 3BHK 83.27 318
3 3BHK 85.96 401
3 3BHK(3T) 89.36 402
3 2BHK 65.52 403
3 2BHK 65.52 404
3 3BHK 83.27 405
3 3BHK 80.78 406
3 3BHK 83.27 407
3 3BHK 81.29 408
3 2BHK 64.96 409
3 2BHK+STUDY 69.26 410
3 2.5BHK 73.01 411
3 2BHK 64.96 412
3 1BHK 40.91 413
3 1BHK 40.91 414
3 3BHK 83.27 415
3 2BHK+STUDY 69.26 416
3 3BHK 80.59 417
3 3BHK 83.27 418
4 3BHK 85.96 501
4 3BHK(3T) 89.36 502
4 2BHK 65.52 503
4 2BHK 65.52 504
4 3BHK 83.27 505
4 3BHK 80.78 506
4 3BHK 83.27 507
4 3BHK 81.29 508
4 2BHK 64.96 509
4 2BHK+STUDY 69.26 510
4 2.5BHK 73.01 511
4 2BHK 64.96 512
4 1BHK 40.91 513
4 1BHK 40.91 514
4 3BHK 83.27 515
4 2BHK+STUDY 69.26 516
4 3BHK 80.59 517
4 3BHK 83.27 518
5 3BHK 85.96 601
5 3BHK(3T) 89.36 602
5 2BHK 65.52 603
5 2BHK 65.52 604
5 3BHK 83.27 605
5 3BHK 80.78 606
5 3BHK 83.27 607
5 3BHK 81.29 608
5 2BHK 64.96 609
5 2BHK+STUDY 69.26 610
5 2.5BHK 73.01 611
5 2BHK 64.96 612
5 1BHK 40.91 613
5 1BHK 40.91 614
5 3BHK 83.27 615
5 2BHK+STUDY 69.26 616
5 3BHK 80.59 617
5 3BHK 83.27 618
6 3BHK 85.96 701
6 3BHK(3T) 89.36 702
6 2BHK 65.52 703
6 2BHK 65.52 704
6 3BHK 83.27 705
6 3BHK 80.78 706
6 3BHK 83.27 707
6 3BHK 81.29 708
6 2BHK 64.96 709
6 2BHK+STUDY 69.26 710
6 2.5BHK 73.01 711
6 2BHK 64.96 712
6 1BHK 40.91 713
6 1BHK 40.91 714
6 3BHK 83.27 715
6 2BHK+STUDY 69.26 716
6 3BHK 80.59 717
6 3BHK 83.27 718
7 3BHK 85.96 801
7 3BHK(3T) 89.36 802
7 2BHK 65.52 803
7 2BHK 65.52 804
7 3BHK 83.27 805
7 3BHK 80.78 806
7 3BHK 83.27 807
7 3BHK 81.29 808
7 2BHK 64.96 809
7 2BHK+STUDY 69.26 810
7 2.5BHK 73.01 811
7 2BHK 64.96 812
7 1BHK 40.91 813
7 1BHK 40.91 814
7 3BHK 83.27 815
7 2BHK+STUDY 69.26 816
7 3BHK 80.59 817
7 3BHK 83.27 818
8 3BHK 85.96 901
8 3BHK(3T) 89.36 902
8 2BHK 65.52 903
8 2BHK 65.52 904
8 3BHK 83.27 905
8 3BHK 80.78 906
8 3BHK 83.27 907
8 3BHK 81.29 908
8 2BHK 64.96 909
8 2BHK+STUDY 69.26 910
8 2.5BHK 73.01 911
8 2BHK 64.96 912
8 1BHK 40.91 913
8 1BHK 40.91 914
8 3BHK 83.27 915
8 2BHK+STUDY 69.26 916
8 3BHK 80.59 917
8 3BHK 83.27 918
9 3BHK 85.96 1001
9 3BHK(3T) 89.36 1002
9 2BHK 65.52 1003
9 2BHK 65.52 1004
9 3BHK 83.27 1005
9 3BHK 80.78 1006
9 3BHK 83.27 1007
9 3BHK 81.29 1008
9 2BHK 64.96 1009
9 2BHK+STUDY 69.26 1010
9 2.5BHK 73.01 1011
9 2BHK 64.96 1012
9 1BHK 40.91 1013
9 1BHK 40.91 1014
9 3BHK 83.27 1015
9 2BHK+STUDY 69.26 1016
9 3BHK 80.59 1017
9 3BHK 83.27 1018
10 3BHK 85.96 1101
10 3BHK(3T) 89.36 1102
10 2BHK 65.52 1103
10 2BHK 65.52 1104
10 3BHK 83.27 1105
10 3BHK 80.78 1106
10 3BHK 83.27 1107
10 3BHK 81.29 1108
10 2BHK 64.96 1109
10 2BHK+STUDY 69.26 1110
10 2.5BHK 73.01 1111
10 2BHK 64.96 1112
10 1BHK 40.91 1113
10 1BHK 40.91 1114
10 3BHK 83.27 1115
10 2BHK+STUDY 69.26 1116
10 3BHK 80.59 1117
10 3BHK 83.27 1118
11 3BHK 85.96 1201
11 3BHK(3T) 89.36 1202
11 2BHK 65.52 1203
11 2BHK 65.52 1204
11 3BHK 83.27 1205
11 3BHK 80.78 1206
11 3BHK 83.27 1207
11 3BHK 81.29 1208
11 2BHK 64.96 1209
11 2BHK+STUDY 69.26 1210
11 2.5BHK 73.01 1211
11 2BHK 64.96 1212
11 1BHK 40.91 1213
11 1BHK 40.91 1214
11 3BHK 83.27 1215
11 2BHK+STUDY 69.26 1216
11 3BHK 80.59 1217
11 3BHK 83.27 1218
12 3BHK 85.96 1301
12 3BHK(3T) 89.36 1302
12 2BHK 65.52 1303
12 2BHK 65.52 1304
12 3BHK 83.27 1305
12 3BHK 80.78 1306
12 3BHK 83.27 1307
12 3BHK 81.29 1308
12 2BHK 64.96 1309
12 2BHK+STUDY 69.26 1310
12 2.5BHK 73.01 1311
12 2BHK 64.96 1312
12 1BHK 40.91 1313
12 1BHK 40.91 1314
12 3BHK 83.27 1315
12 2BHK+STUDY 69.26 1316
12 3BHK 80.59 1317
12 3BHK 83.27 1318
13 3BHK 85.96 1401
13 3BHK(3T) 89.36 1402
13 2BHK 65.52 1403
13 2BHK 65.52 1404
13 3BHK 83.27 1405
13 3BHK 80.78 1406
13 3BHK 83.27 1407
13 3BHK 81.29 1408
13 2BHK 64.96 1409
13 2BHK+STUDY 69.26 1410
13 2.5BHK 73.01 1411
13 2BHK 64.96 1412
13 1BHK 40.91 1413
13 1BHK 40.91 1414
13 3BHK 83.27 1415
13 2BHK+STUDY 69.26 1416
13 3BHK 80.59 1417
13 3BHK 83.27 1418
14 3BHK 85.96 1501
14 3BHK(3T) 89.36 1502
14 2BHK 65.52 1503
14 2BHK 65.52 1504
14 3BHK 83.27 1505
14 3BHK 80.78 1506
14 3BHK 83.27 1507
14 3BHK 81.29 1508
14 2BHK 64.96 1509
14 2BHK+STUDY 69.26 1510
14 2.5BHK 73.01 1511
14 2BHK 64.96 1512
14 1BHK 40.91 1513
14 1BHK 40.91 1514
14 3BHK 83.27 1515
14 2BHK+STUDY 69.26 1516
14 3BHK 80.59 1517
14 3BHK 83.27 1518
15 3BHK 85.96 1601
15 3BHK(3T) 89.36 1602
15 2BHK 65.52 1603
15 2BHK 65.52 1604
15 3BHK 83.27 1605
15 3BHK 80.78 1606
15 3BHK 83.27 1607
15 3BHK 81.29 1608
15 2BHK 64.96 1609
15 2BHK+STUDY 69.26 1610
15 2.5BHK 73.01 1611
15 2BHK 64.96 1612
15 1BHK 40.91 1613
15 1BHK 40.91 1614
15 3BHK 83.27 1615
15 2BHK+STUDY 69.26 1616
15 3BHK 80.59 1617
15 3BHK 83.27 1618
16 3BHK 85.96 1701
16 3BHK(3T) 89.36 1702
16 2BHK 65.52 1703
16 2BHK 65.52 1704
16 3BHK 83.27 1705
16 3BHK 80.78 1706
16 3BHK 83.27 1707
16 3BHK 81.29 1708
16 2BHK 64.96 1709
16 2BHK+STUDY 69.26 1710
16 2.5BHK 73.01 1711
16 2BHK 64.96 1712
16 1BHK 40.91 1713
16 1BHK 40.91 1714
16 3BHK 83.27 1715
16 2BHK+STUDY 69.26 1716
16 3BHK 80.59 1717
16 3BHK 83.27 1718
17 3BHK 85.96 1801
17 3BHK(3T) 89.36 1802
17 2BHK 65.52 1803
17 2BHK 65.52 1804
17 3BHK 83.27 1805
17 3BHK 80.78 1806
17 3BHK 83.27 1807
17 3BHK 81.29 1808
17 2BHK 64.96 1809
17 2BHK+STUDY 69.26 1810
17 2.5BHK 73.01 1811
17 2BHK 64.96 1812
17 1BHK 40.91 1813
17 1BHK 40.91 1814
17 3BHK 83.27 1815
17 2BHK+STUDY 69.26 1816
17 3BHK 80.59 1817
17 3BHK 83.27 1818
18 3BHK 85.96 1901
18 3BHK(3T) 89.36 1902
18 2BHK 65.52 1903
18 2BHK 65.52 1904
18 3BHK 83.27 1905
18 3BHK 80.78 1906
18 3BHK 83.27 1907
18 3BHK 81.29 1908
18 2BHK 64.96 1909
18 2BHK+STUDY 69.26 1910
18 2.5BHK 73.01 1911
18 2BHK 64.96 1912
18 1BHK 40.91 1913
18 1BHK 40.91 1914
18 3BHK 83.27 1915
18 2BHK+STUDY 69.26 1916
18 3BHK 80.59 1917
18 3BHK 83.27 1918
19 3BHK 85.96 2001
19 3BHK(3T) 89.36 2002
19 2BHK 65.52 2003
19 2BHK 65.52 2004
19 3BHK 83.27 2005
19 3BHK 80.78 2006
19 3BHK 83.27 2007
19 3BHK 81.29 2008
19 2BHK 64.96 2009
19 2BHK+STUDY 69.26 2010
19 2.5BHK 73.01 2011
19 2BHK 64.96 2012
19 1BHK 40.91 2013
19 1BHK 40.91 2014
19 3BHK 83.27 2015
19 2BHK+STUDY 69.26 2016
19 3BHK 80.59 2017
19 3BHK 83.27 2018
20 3BHK 85.96 2101
20 3BHK(3T) 89.36 2102
20 2BHK 65.52 2103
20 2BHK 65.52 2104
20 3BHK 83.27 2105
20 3BHK 80.78 2106
20 3BHK 83.27 2107
20 3BHK 81.29 2108
20 2BHK 64.96 2109
20 2BHK+STUDY 69.26 2110
20 2.5BHK 73.01 2111
20 2BHK 64.96 2112
20 1BHK 40.91 2113
20 1BHK 40.91 2114
20 3BHK 83.27 2115
20 2BHK+STUDY 69.26 2116
20 3BHK 80.59 2117
20 3BHK 83.27 2118
21 3BHK 85.96 2201
21 3BHK(3T) 89.36 2202
21 2BHK 65.52 2203
21 2BHK 65.52 2204
21 3BHK 83.27 2205
21 3BHK 80.78 2206
21 3BHK 83.27 2207
21 3BHK 81.29 2208
21 2BHK 64.96 2209
21 2BHK+STUDY 69.26 2210
21 2.5BHK 73.01 2211
21 2BHK 64.96 2212
21 1BHK 40.91 2213
21 1BHK 40.91 2214
21 3BHK 83.27 2215
21 2BHK+STUDY 69.26 2216
21 3BHK 80.59 2217
21 3BHK 83.27 2218
22 3BHK 85.96 2301
22 3BHK(3T) 89.36 2302
22 2BHK 65.52 2303
22 2BHK 65.52 2304
22 3BHK 83.27 2305
22 3BHK 80.78 2306
22 3BHK 83.27 2307
22 3BHK 81.29 2308
22 2BHK 64.96 2309
22 2BHK+STUDY 69.26 2310
22 2.5BHK 73.01 2311
22 2BHK 64.96 2312
22 1BHK 40.91 2313
22 1BHK 40.91 2314
22 3BHK 83.27 2315
22 2BHK+STUDY 69.26 2316
22 3BHK 80.59 2317
22 3BHK 83.27 2318
23 3BHK 85.96 2401
23 3BHK(3T) 89.36 2402
23 2BHK 65.52 2403
23 2BHK 65.52 2404
23 3BHK 83.27 2405
23 3BHK 80.78 2406
23 3BHK 83.27 2407
23 3BHK 81.29 2408
23 2BHK 64.96 2409
23 2BHK+STUDY 69.26 2410
23 2.5BHK 73.01 2411
23 2BHK 64.96 2412
23 1BHK 40.91 2413
23 1BHK 40.91 2414
23 3BHK 83.27 2415
23 2BHK+STUDY 69.26 2416
23 3BHK 80.59 2417
23 3BHK 83.27 2418
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage - - -
Covered Parking - - -
Open Parking - - -
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Sub Structure Earth Work And Other Leveling Preparation Work % not reported Sub Structure Foundation Footing Work % not reported Sub Structure Upto Plinth Level % not reported
Sub Structure Sub-structure Flooring (Parking Floor, More Than One Floor Below General Ground Level) % not reported Sub Structure Retaining Wall (All Types) % not reported Sup Structure Rcc Or Ms Framed Structure % not reported
Sup Structure Masonry Construction % not reported Sup Structure Plastering Inside , Outside & Ceiling % not reported Sup Structure Joinery: Doors, Windows, Ventilators Etc % not reported
Sup Structure Basic Work Of Water Supply, Sanitary And Electrification % not reported Sup Structure Dadoing, Skirting, Flooring, Tiles Work (All Types) % not reported Sup Structure Railing And Grill Fixing % not reported
Finishing Works Electrification, Water Supply And Sanitary Finishing % not reported Finishing Works Painting % not reported Finishing Works Fire Prevention And Fire Fighting Fitting And Fixture With Network % not reported
Finishing Works Weather Proof Work(tile,concrete) % not reported Finishing Works Wardrobe, Showcase, Kitchen Cabinet, Puja Work % not reported Finishing Works Elevation Work % not reported
Finishing Works Internal And External Work Including Landscapes As Per Sanctioned Drawings % not reported Internal Infrastructure Water Supply % not reported Internal Infrastructure Sewage And Drainage System % not reported
Internal Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported Internal Infrastructure Energy Management % not reported Internal Infrastructure Fire Protection And Fire Safety Requirements % not reported
Internal Infrastructure Solid Waste Management And Disposal % not reported Internal Infrastructure Emergency Evacuation Services % not reported External Infrastructure Water Supply % not reported
External Infrastructure Internal Roads & Footpaths % not reported External Infrastructure Sewage And Drainage System % not reported External Infrastructure Electricity Supply Transformer And Substation % not reported
External Infrastructure Solid Waste Management And Disposal % not reported External Infrastructure Emergency Evacuation Services % not reported External Infrastructure Storm Water Drains % not reported
External Infrastructure Use Of Renewable Energy % not reported External Infrastructure Water Conservation/rain Water Harvesting/recharge Of Ground Water % not reported External Infrastructure Fire Protection And Fire Safety Requirements % not reported
External Infrastructure Sewage Treatment Plant (Stp) % not reported External Infrastructure Parks & Tree Planting % not reported External Infrastructure Street Lighting % not reported
Amenities Electricity % not reported Amenities Smart Home Automation % not reported Amenities Cctv Surveillance % not reported
Amenities Club House % not reported Amenities Community Hall % not reported Amenities Outdoor Sports Facility % not reported
Amenities Indoor Sports Facility % not reported Amenities Swimming Pool % not reported Amenities Gym % not reported
Amenities Parks % not reported Amenities Power Backup % not reported Amenities Piped Gas % not reported
Amenities Water And Sanitation % not reported Amenities Air Conditioning % not reported Common Areas Staircases % not reported
Common Areas Lifts % not reported Common Areas Corridor/lobbies % not reported Common Areas Fire Escapes % not reported
Common Areas Common Entrance And Exit For The Building/common Portico/foyer/verandah % not reported Common Areas Basement % not reported Common Areas Terrace % not reported
Common Areas Outer Wall % not reported Common Areas Open Parking Areas % not reported Common Areas Provision For Lodging Of Management Staff And Security Staff % not reported
Common Areas Water Conservation And Renewable Energy % not reported Common Areas Common Storage Spaces % not reported
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Promoter Registration Certificate
Promoter Pan Card
Promoter Address Proof
Affidavit
Fd 1 TRIFECTA Balance Sheet-2023.Pdf
Fd 2 TRIFECTA Balance Sheet-2022.Pdf
Fd 3 TRIFECTA Balance Sheet-2021.Pdf
Fd 4 TRIFECTA P-L-2023.Pdf
Fd 5 TRIFECTA P L -2022.Pdf
Fd 6 TRIFECTA P L -2021.Pdf
Fd 7 FY 22-23.Pdf
Fd 8 TRIFECTA P L -2022.Pdf
Fd 9 Direct Report 2021 Compressed.Pdf
Fd 10 TRIFECTA CF 2022-23.Pdf
Fd 11 TRIFECTA CF 2021-22.Pdf
Fd 12 TRIFECTA CF 2020-21.Pdf
Fd 13 AR 22-23 Compressed (1).Pdf
Fd 14 Audit Report 21-22 Compressed.Pdf
Fd 15 Audit Report 2021 Compressed.Pdf
Fd 16 ITR 2022-23.Pdf
Fd 17 ITR V 21-22.Pdf
Fd 18 ITR 2020-21.Pdf
Pd 1 Self Attested PAN Card*( Annexure - 66 )
Pd 2 Commencement Certificate*( Annexure - 67 )
Pd 3 Electricity Permission Letter*( Annexure - 68 )
Pd 4 Water Permission Letter*( Annexure - 69 )
Pd 5 Approved Layout Plan*( Annexure - 70 )
Pd 6 Approved Building Plotting Plan*( Annexure - 71 )
Pd 7 Existing Layout Plan( Annexure - 72 )
Pd 8 Existing Section Plan And Specification( Annexure - 73 )
Pd 9 Sectional Drawing Of The Apartments*( Annexure - 74 )
Pd 10 Project Specifications*( Annexure - 75 )
Pd 11 Approved Section Of Building Infrastructure Plan Of Plotting*( Annexure - 76 )
Pd 12 Area Development Plan Of Project Area*( Annexure - 77 )
Pd 13 Certificate From Registered Engineer Indicating The Structural Safety Of The Building*( Annexure - 78 )
Pd 14 Advocate Search Report*( Annexure - 79 )
Pd 15 Urban Land Ceiling*( Annexure - 80 )
Od 19 Plan Approval For Club House.Pdf
Pd 16 Collaboration Agreement Development Agreement Joint Development Agreement Other Agreement*( Annexure - 81 )
Pd 17 Change Of Land Use*( Annexure - 82 )
Pd 18 District Magistrate*( Annexure - 83 )
Pd 19 Conversion Certificate Under Section 95 Of The KLR Act 1964*( Annexure - 84 )
Pd 20 Any Other Document (Rights Title Interest Name)*( Annexure - 85 )
Pd 21 Proforma Of Agreement For Sale*( Annexure - 86 )
Pd 22 Proforma Of Allotment Letter*( Annexure - 87 )
Pd 24 Brochure*( Annexure - 89 )
Dc 1 Declaration (Form B)*( Annexure - 90 )
Dc 2 Section 3(1) Notarized Affidavit*( Annexure - 91 )
Dc 3 JD AFFIDAVIT CUM DECLARATION*( Annexure - 92 )
Noc 1 ESCOM Electricity*( Annexure - 93 )
Noc 2 KWSSB Water*( Annexure - 94 )
Noc 3 Approval NOC Under Section 109 Of KLR Act 1961( Annexure - 95 )
Noc 4 Approval NOC Under Section 14 Of The KTCP Act( Annexure - 96 )
Noc 5 Fire Force Department( Annexure - 97 )
Noc 6 Airport Authority Of India( Annexure - 98 )
Noc 7 KSPCB( Annexure - 99 )
Noc 8 SEIAA( Annexure - 100 )
Noc 9 BSNL( Annexure - 101 )
Noc 10 Lift Authorities( Annexure - 102 )
Noc 11 BMRCL( Annexure - 103 )
Noc 12 NOC In Case Of Building Proposals Abutting To Neighbouring Properties( Annexure - 104 )
Noc 13 Bangalore Urban Arts Commission( Annexure - 105 )
Noc 14 Inspector Of Factories Controller Of Explosives Railways( Annexure - 106 )
Noc 15 Coastal Regulation Zone Authority( Annexure - 107 )
Dr 1 Utilisation Certificate( Annexure - 108 )
Dr 2 Transfer Of Development Rights Certificate( Annexure - 109 )
Dr 3 Relinquishment Deed( Annexure - 110 )
Photo 1 Project Photo
Od 1 Vanto Project Photos.Pdf
Od 2 NOC Fire.Pdf
Od 3 0 Plan Basement FLoor.Pdf
Od 4 1 Plan Site.Pdf
Od 5 2 Plan Ground Floor 1.Pdf
Od 6 3 Plan Ground Floor 2.Pdf
Od 7 4 Plan First Floor.Pdf
Od 8 5 Plan Second Floor.Pdf
Od 9 6 Plan 3 To 18 & 20 To 24 Typical Floor.Pdf
Od 10 7 Plan 19th Floor.Pdf
Od 11 8 Plan Terrace FLoor.Pdf
Od 12 9 Plan Block A Section.Pdf
Od 13 10 Plan Block A Elevation.Pdf
Od 14 11 Plan Club House Section, Elevation And Site.Pdf
Od 15 12 Plan Club House G & B.Pdf
Od 16 13 Plan Club House 1st, 2nd & Terrace Compressed.Pdf
Od 17 Borewell Photos.Pdf
Od 18 Board Resolution.Pdf
Od 20 Plan Approval For Project.Pdf
Od 21 Sub Reg Guid Val Cert.Pdf
Od 22 Sale Deed 37-19 6G.Pdf
Od 23 JDA 37-8, 7,4,11,6, 9, 5, 10,2, 12 Compressed.Pdf
Od 24 JDA 43-4B 25-5G.Pdf
Od 25 JDA 43-4B 1A 36 08G.Pdf
Od 26 JDA 37-7 2G Compressed.Pdf
Od 27 JDA 37-8, 7,4,11,6, 9, 5, 10,2, 12 Compressed.Pdf
Ed 1 04-04-2024
Ed 2 04-04-2024
Ed 3 04-04-2024
Ed 4 04-04-2024
Ed 5 04-04-2024
Ed 6 04-04-2024
Ed 7 04-04-2024
Ed 8 04-04-2024
Ed 9 04-04-2024
Ed 10 04-04-2024
Ed 11 04-04-2024
Ed 12 04-04-2024
Ed 13 04-04-2024
Ed 14 04-04-2024
Ed 15 04-04-2024
Ed 16 04-04-2024
Ed 17 04-04-2024
Ed 18 04-04-2024
Ed 19 04-04-2024
Ed 20 04-04-2024
Ed 21 04-04-2024
Ed 22 04-04-2024
Ed 23 04-04-2024
Ed 24 04-04-2024
Ed 25 04-04-2024
Ed 26 04-04-2024
Ed 27 04-04-2024
Ed 28 04-04-2024
Ed 29 04-04-2024
Ed 30 04-04-2024
Ed 31 04-04-2024
Ed 32 04-04-2024
Ed 33 17-04-2024
Ed 34 17-04-2024
Ld Rtc
Ld Mutation
Ld Encumbrance Certificate
Ld Conversion Order
Ld Khatha
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Axis Bank
Account Number (RERA) 924020045049443
IFSC UTIB0003075
Branch Address Mahadevapura Branch``
Country/City